A business analyst needs input from a marketing consultant to proceed with a task but the consultant says they don't have time to discuss the project. What should the project manager do to move the work forward?
Choose an answer
Tap an option to check your answer.
Correct answer: Discuss the request with the consultant and schedule a meeting with the business analyst and consultant to review the requirements..
Why this is the answer
The project manager's role is to facilitate work and remove impediments. Discussing the request directly with the consultant demonstrates proactive problem-solving and collaboration. Scheduling a meeting with both parties ensures the necessary input is obtained and fosters teamwork. Escalating immediately (first incorrect option) can be confrontational and may not be necessary at this stage. Adding a risk (second incorrect option) is a reactive measure and doesn't directly solve the immediate communication breakdown. Urging the business analyst to keep contacting the consultant (third incorrect option) is passing the buck and not actively resolving the issue.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed