A company announced a launch date for a new innovative product. After the first sprint planning, the team realizes they cannot deliver all features by the launch date. What should the project manager do to ensure success?
Choose an answer
Tap an option to check your answer.
Correct answer: Assist the team in defining a minimum viable product (MVP) by the launch date..
Why this is the answer
The correct approach is to assist the team in defining a Minimum Viable Product (MVP) by the launch date. In agile environments, when faced with a fixed deadline and an overly ambitious scope, the most effective strategy is to prioritize and deliver the core functionality that provides essential value. This allows the product to launch on time, gather user feedback, and iterate on future releases. Asking the customer to reduce the backlog might be necessary, but defining an MVP is a more proactive and collaborative step that focuses on delivering value. Increasing team capacity late in the game is often impractical, costly, and doesn't guarantee quality or adherence to the fixed deadline. Scheduling a contingency plan review is reactive; a proactive solution like MVP definition is preferred to meet the primary objective.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed