A company has begun using Scrum. Midway through the first sprint, communication breaks down and some team members are out of sync. What is the most likely cause of this communication gap?
Choose an answer
Tap an option to check your answer.
Correct answer: Daily standup meetings were not held or enforced.
Why this is the answer
The most likely cause of a communication breakdown and team members being out of sync midway through a sprint is that daily standup meetings were not held or enforced. Daily standups (or Daily Scrums) are a core Scrum event designed to synchronize team activities, identify impediments, and ensure everyone is aware of progress and plans for the next 24 hours. Without these regular, brief meetings, team members can quickly lose alignment. While an outdated sprint board can contribute to miscommunication, the daily standup is the primary mechanism for verbal synchronization and problem identification. An outdated project status dashboard is more for stakeholders and less for immediate team synchronization within a sprint. A communications management plan is a traditional project management document and, while important for overall project communication, its absence is less likely to cause an immediate breakdown within a Scrum sprint compared to the lack of daily standups.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed