A company merger changed the primary stakeholder for a critical project. The new stakeholder says they were unaware of a project delay that other stakeholders knew about. Project communications are emailed at the start of each week. How should the project manager respond?
Choose an answer
Tap an option to check your answer.
Correct answer: Meet with the new stakeholder to review project requirements and update the communications management plan..
Why this is the answer
The correct response is to meet with the new stakeholder to review project requirements and update the communications management plan. This addresses the immediate issue of the stakeholder being unaware of delays and proactively prevents future communication gaps. Understanding their expectations and incorporating them into the plan ensures effective communication moving forward. Sending evidence of past communications (incorrect option) doesn't solve the underlying problem of the stakeholder being uninformed. Asking them to review status (incorrect option) is reactive and doesn't address the root cause or improve the communication process. Sharing the existing communications management plan (incorrect option) is insufficient because the plan itself likely needs updating to accommodate the new stakeholder's needs and preferences.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed