A company must launch a new product before the summer season. After discovery, the team finds the requirements are highly uncertain. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Help the team propose a minimum viable product (MVP)..
Why this is the answer
When requirements are highly uncertain, an agile approach is best. Proposing a Minimum Viable Product (MVP) allows the team to deliver core value quickly, gather feedback, and iteratively refine future increments. This approach embraces uncertainty by focusing on learning and adaptation. Requesting SMEs might help, but doesn't directly address the uncertainty in requirements or provide a path forward. Logging a risk and creating a contingency plan is a reactive measure for known risks, not a proactive strategy for high uncertainty in requirements. Inviting stakeholders to prioritize requirements is a good practice, but without further discovery or an iterative approach, it won't resolve high uncertainty.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed