A construction firm won a bid to build a cable bridge. With a project charter and assigned project manager, the manager is creating the WBS. To what level should the project be decomposed?
Choose an answer
Tap an option to check your answer.
Correct answer: To the lowest level where cost and duration can be estimated and managed.
Why this is the answer
The Work Breakdown Structure (WBS) decomposes project work into smaller, manageable components. The correct level of decomposition is the work package, which is the lowest level where cost and duration can be reliably estimated and managed. This allows for effective control and monitoring of the project. Decomposing to a level based on quality or safety, while important project considerations, isn't the primary driver for WBS decomposition. Similarly, decomposing to a specific schedule level (like "level four") is arbitrary and doesn't align with the WBS's purpose of defining the scope of work.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed