A customer has given excellent feedback on the project, but a key project resource is leaving the company. Which measure should mitigate the impact of this resource's departure?
Choose an answer
Tap an option to check your answer.
Correct answer: Establish a proactive knowledge-sharing plan.
Why this is the answer
Establishing a proactive knowledge-sharing plan is the most effective measure to mitigate the impact of a key resource's departure. This ensures that critical information, processes, and expertise are documented and transferred to other team members before the resource leaves, minimizing disruption and maintaining project continuity. Offering a new contract might retain the resource, but it's reactive and doesn't address the underlying risk of single points of failure. Allocating a contingency budget for replacement is a financial measure, not a direct mitigation of the knowledge loss. While updating the risk register and informing the customer are good practices for transparency and risk management, they do not actively prevent or reduce the operational impact of the resource's departure.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed