A global project team will work virtually and faces language and time zone challenges, though each member is an expert. What should the project manager do first to address these challenges?
Choose an answer
Tap an option to check your answer.
Correct answer: Investigate alternatives for virtual meeting times and written communication methods..
Why this is the answer
The project manager's first step should be to investigate alternatives for virtual meeting times and written communication methods. This proactive approach directly addresses the identified challenges of time zones and language barriers by exploring practical solutions. It's an initial information-gathering and planning step that can lead to effective strategies. Scheduling meetings at times when all members can attend might not be feasible or sustainable for all team members due to extreme time differences, and it doesn't address language barriers. Engaging HR for relocation is a drastic and likely impractical measure for a global virtual team, and it's not the first step to address communication challenges. Reviewing the communications management plan to assign a facilitator is a good step, but it comes after understanding the scope of the problem and potential solutions through initial investigation.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed