A globally distributed development team experienced a delayed important release because one developer missed an email sent to everyone. To prevent this in the future, what should the project manager review?
Choose an answer
Tap an option to check your answer.
Correct answer: Review the communications management plan..
Why this is the answer
The correct answer is to review the communications management plan. This plan details how project information will be communicated, including methods, frequency, and recipients. A missed email indicates a breakdown in the current communication strategy, suggesting the plan may need adjustments to ensure all team members receive critical updates, especially in a globally distributed environment where different time zones and communication preferences exist. Reviewing the stakeholder engagement plan is incorrect because while stakeholders are involved, this specific issue points to an internal team communication failure, not a broader engagement problem. Reviewing the resource management plan is incorrect as it focuses on acquiring, developing, and managing project resources, not the methods of information exchange. Reviewing the risk management plan is incorrect because while communication failures can be risks, the immediate action is to address the communication process itself, which is governed by the communications management plan.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed