A government-owned project used an iterative approach; the first production release included three iterations, each validated by client representatives in a test environment, but the security team rejected deployment to production. What should the project manager have done to prevent this?
Choose an answer
Tap an option to check your answer.
Correct answer: Review the compliance requirements with stakeholders..
Why this is the answer
The project manager should have reviewed compliance requirements with stakeholders, including the security team, early in the project. This proactive engagement ensures that all necessary security and regulatory standards are understood and incorporated into the development process from the beginning. By involving the security team, their concerns could have been addressed during the initial iterations, preventing a last-minute rejection. Implementing authorization in the first iteration might be a technical solution but doesn't address the root cause of not understanding the security team's requirements. Deploying to production after the first iteration would likely lead to the same rejection, just sooner, as the security concerns weren't addressed. Planning smaller iterations doesn't inherently solve the problem of unaddressed compliance requirements; the same issues would resurface, just more frequently.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed