A graph shows the project's current cost and schedule performance. What should the project manager do to bring the project back on track?
Choose an answer
Tap an option to check your answer.
Correct answer: Review project schedule because the project is under budget and behind schedule..
Why this is the answer
The correct answer is to review the project schedule because the project is under budget and behind schedule. This scenario implies a Cost Performance Index (CPI) greater than 1 (under budget) and a Schedule Performance Index (SPI) less than 1 (behind schedule). The project has spent less than planned for the work completed, but has completed less work than planned by this point. The primary concern is the schedule delay, which could impact project objectives and stakeholder expectations. Reviewing the schedule will help identify the root causes of the delay and develop corrective actions to accelerate progress. The other options describe different performance scenarios or incorrect responses to the given scenario.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed