A hybrid project is encountering problems with agile product delivery and predictive marketing development. The project manager needs feedback from stakeholders in different time zones. What should the project manager consult or do?
Choose an answer
Tap an option to check your answer.
Correct answer: Refer to the communications management plan..
Why this is the answer
The Communications Management Plan details how, when, and by whom project information will be administered and distributed. It includes strategies for communicating with stakeholders in different time zones and for various project phases (agile product delivery, predictive marketing development). Consulting this plan ensures the project manager uses established, effective communication methods tailored to the project's specific needs and stakeholder requirements, rather than improvising. Sending a generic email or setting up a single conference call might not be effective for stakeholders in diverse time zones or with varying communication preferences, and the stakeholder engagement plan focuses more on how to involve stakeholders rather than the specific communication methods.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed