A junior project manager asks a senior project manager during coaching how to be efficient and reduce rework. How should the senior project manager respond?
Choose an answer
Tap an option to check your answer.
Correct answer: Use a work breakdown structure (WBS) to build a project schedule based on project and resource requirements..
Why this is the answer
The correct answer is to use a WBS to build a project schedule based on project and resource requirements. A WBS is a foundational tool for project planning, breaking down project work into manageable components. This structured approach ensures all necessary work is identified, reducing the likelihood of missed tasks and subsequent rework. By linking the WBS to the schedule and considering resource requirements, the project manager can create a realistic and efficient plan. Monitoring resource allocation to ensure team members work eight hours per day is not an effective way to reduce rework; it focuses on hours, not quality or efficiency. Assigning tasks without regard to skills is detrimental to quality and will likely increase rework. Scheduling daily meetings with key stakeholders to evaluate the project management plan's effectiveness is excessive and inefficient for daily operations, though stakeholder engagement is important at appropriate intervals.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed