A key stakeholder complains that recent project communications were incomplete and late, and is beginning to disengage. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Update the communications management plan to fulfill the key stakeholder's expectations about relevant information..
Why this is the answer
The project manager should update the communications management plan because it's a proactive and structured approach to address the stakeholder's concerns directly. The plan defines how, when, and by whom project information will be communicated. Revising it ensures that the stakeholder's needs for complete and timely information are formally incorporated and consistently met going forward, thereby restoring engagement. Explaining current communication methods without addressing the underlying issue won't resolve the problem. Sending all information simultaneously might not be tailored to individual stakeholder needs and could lead to information overload. Asking the project sponsor to intervene is a reactive escalation that doesn't address the root cause of the communication breakdown.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed