A multiyear, resource-constrained project is mid-execution. In a progress meeting a potential schedule delay is identified, although the team is working hard and many deliverables are complete. What should the project manager do immediately?
Choose an answer
Tap an option to check your answer.
Correct answer: Ask the project planner to identify the critical path and the delayed activities, then investigate the reasons for the delay..
Why this is the answer
The project manager's immediate action should be to understand the extent and cause of the potential delay. Asking the project planner to identify the critical path and delayed activities will pinpoint where the schedule is truly impacted. Investigating the reasons for the delay is crucial for developing an effective solution, rather than reacting prematurely. Registering the risk and presenting new resource requirements (A) is premature without understanding the root cause and impact. Preparing a monthly report (B) is a reporting function, not an immediate problem-solving step. Updating the schedule with WIP (D) is part of routine tracking but doesn't address the cause of the potential delay or provide a path forward.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed