A new major road project’s contractor contractually agreed to submit regular status reports and attend integration meetings. Midway through the project they stop attending meetings and submitting reports, saying it takes too much time. What should the project manager do first?
Choose an answer
Tap an option to check your answer.
Correct answer: Remind the contractor that they contractually agreed to attend meetings and submit reports.
Why this is the answer
The project manager should first remind the contractor of their contractual obligations. This is the most direct and least escalatory approach to address the issue. It allows for a direct conversation to understand the contractor's concerns and find a mutually agreeable solution before escalating. Assessing risk and escalating to the sponsor, submitting a claim, or consulting a lawyer are all more severe actions that should be considered only if direct communication fails to resolve the issue. These options bypass the opportunity for a simple resolution and could damage the working relationship unnecessarily.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed