A new project manager finds the work has been decomposed to the lowest level, but believes some useful information is missing. What should the project manager review?
Choose an answer
Tap an option to check your answer.
Correct answer: The WBS dictionary.
Why this is the answer
The WBS dictionary provides detailed information for each WBS component, including work package descriptions, deliverables, acceptance criteria, assigned organization, schedule milestones, and cost estimates. If the project manager feels useful information is missing despite the WBS being decomposed, the WBS dictionary is the primary document to consult for these specifics. The requirements traceability matrix links requirements to deliverables but doesn't detail work package specifics. The project charter and scope statement define the overall project and its boundaries but not the detailed work package information. Business requirement documents (BRDs) define stakeholder needs but are not the source for detailed WBS component information.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed