A new project manager is creating a time-sensitive social media strategy and the stakeholder communications management plan for a software company that is now fully remote. An existing standard operating procedure (SOP) describes how communications should occur. How should the project manager proceed?
Choose an answer
Tap an option to check your answer.
Correct answer: Assess the SOP for relevancy, update it as needed, and circulate it to stakeholders for comment during project planning..
Why this is the answer
The correct approach is to assess the existing SOP for relevancy, update it as needed to fit the current project's specific requirements (especially considering the new remote work environment and time-sensitive nature), and then circulate it to stakeholders for their input during the planning phase. This ensures the communications plan is tailored, effective, and has stakeholder buy-in. Following the SOP blindly and escalating changes later is reactive and inefficient. Using it as a baseline and updating during monitoring and controlling is too late for effective planning. Ignoring it completely is poor project management practice, as it disregards organizational process assets.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed