A new project manager sees the team replacing an old system includes members experienced with the old system and others with little experience. What should the project manager do to ensure success?
Choose an answer
Tap an option to check your answer.
Correct answer: Evaluate the current effectiveness of the team and define development needs..
Why this is the answer
The project manager should evaluate the team's current effectiveness and define development needs to ensure success. This proactive approach identifies skill gaps between those experienced with the old system and those new to it, allowing for targeted training, mentoring, or cross-training. This ensures all team members can contribute effectively and the project benefits from a well-rounded skill set. Assigning roles solely based on past experience might underutilize new talent or create silos. Allowing individual strengths without addressing overall project needs could lead to critical skill gaps. Requesting a performance assessment from a functional manager is a reactive measure and doesn't directly address the immediate need for team development within the project context.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed