A new project manager takes over a project mid-implementation. At the first risk review, the manager notices team members are using a different version of the risk register than the one the manager has. What should the manager have done to prevent this?
Choose an answer
Tap an option to check your answer.
Correct answer: Validated the project artifacts.
Why this is the answer
The project manager should have validated the project artifacts, including the risk register, during the project handover. This ensures all project documentation is current and consistent, preventing discrepancies like different versions of key documents. Consulting the communications management plan would help understand how information should be shared, but wouldn't proactively identify existing inconsistencies in documents. Validating the issue log is important but focuses on problems, not the overall consistency of project documentation. Applying expert judgment is a technique, but it needs to be applied to specific actions, such as validating artifacts, to be effective in this scenario.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed