A new team member joins an agile project, replacing someone who left. The team needs the new member to become productive quickly. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Schedule knowledge transfer sessions and assign less complex tasks to the new team member.
Why this is the answer
Scheduling knowledge transfer sessions and assigning less complex tasks is the most effective approach to quickly integrate a new agile team member. Knowledge transfer ensures the new member understands the project context, processes, and current work. Starting with less complex tasks allows them to gain confidence, learn the team's workflow, and contribute without being overwhelmed, fostering productivity. Assigning the same tasks as the previous member might be too challenging without proper onboarding. Sending documentation alone is passive and less effective than interactive knowledge transfer. Delaying training until the next iteration or focusing solely on company-wide mandatory training delays their ability to contribute to the project.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed