A new zoning-permit law for telecom towers could cause cost and schedule overruns for the network rollout. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Assess and prioritize the impact of the new law on the project plan.
Why this is the answer
The correct answer is to assess and prioritize the impact of the new law on the project plan. This aligns with proactive risk management. The new zoning law is an external event that introduces a new risk or changes existing risks. The project manager must first understand the full implications (cost, schedule, scope, quality, resources) before deciding on a course of action. Simply requesting more time and budget without analysis is premature. Reducing scope might not be necessary or desirable. Updating the project plan immediately without assessment is also premature, as the impact needs to be understood and a response planned first.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed