A newly assigned project manager finds team performance below target, tasks not delivered on time, and weak team commitment. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Study and determine the appropriate leadership style suitable for the team..
Why this is the answer
The project manager is facing a complex issue with team performance, on-time delivery, and commitment. Before taking any specific action, it's crucial to understand the root cause. Different teams respond to different leadership styles. A project manager must assess the team's maturity, experience, and the project's context to determine the most effective approach. This foundational step allows for an informed decision on how to address the performance gaps. Scheduling a meeting to communicate concerns (first option) is a valid step, but without understanding the underlying issues or the team's needs, it might not be effective or could even demotivate the team further. Hiring a team leader (second option) is a drastic measure that bypasses the project manager's responsibility to lead and understand their team. Applying an agile approach (third option) might be beneficial in some contexts, but it's a solution without a diagnosed problem; it might not be the right fit for the team or project, and it doesn't address the leadership gap.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed