A PMO is adopting adaptive practices and hired a hybrid-experienced project manager, but the team is slow to update artifacts. What should the project manager do to improve team performance?
Choose an answer
Tap an option to check your answer.
Correct answer: Hold a training session for all project team members..
Why this is the answer
The best approach is to hold a training session for all project team members. This addresses the root cause of the slow updates, which is likely a lack of understanding or proficiency with the new adaptive practices and artifact requirements. Training provides a structured opportunity to educate the team, clarify expectations, and demonstrate the value of these updates, leading to improved performance. Sending an email is passive and unlikely to resolve underlying issues or provide necessary instruction. Talking individually might be time-consuming and inconsistent, potentially leading to varied understanding. Contacting functional managers might escalate the issue prematurely without first attempting to resolve it within the team, and it doesn't directly address the team's skill gap.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed