A primary stakeholder cannot consistently attend status meetings. The project manager has been updating them informally and regularly, but the project manager is resigning and will not brief the incoming manager. How should the project manager ensure the new manager continues these updates?
Choose an answer
Tap an option to check your answer.
Correct answer: Update the stakeholder engagement plan with the specific communication needs for the stakeholder.
Why this is the answer
The correct answer is to update the stakeholder engagement plan. This plan details strategies for engaging stakeholders based on their needs and impact. By documenting the specific informal communication approach for this primary stakeholder, the new project manager will have clear guidance to continue effective engagement. Updating the communications management plan is incorrect because while it defines how project information will be communicated, the engagement strategy for specific stakeholders, especially those with unique needs, belongs in the stakeholder engagement plan. Ensuring the project team has guidance is a good operational step but doesn't guarantee the new manager will be aware or that the guidance is formally documented. Updating project documents generally is too vague; the stakeholder engagement plan is the specific document for this purpose.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed