A product is in its final incremental iteration and the team is ready for final deployment. The financial manager asks to finish deployment and close the project quickly so it can be capitalized. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Verify the project's definition of done (DoD)..
Why this is the answer
The project manager should verify the project's Definition of Done (DoD). The DoD is a critical artifact in agile projects, outlining all criteria that must be met for a product increment to be considered complete and ready for release. Before rushing deployment due to external pressure, the project manager must ensure all agreed-upon quality and completeness standards are met. Expediting deployment without verification risks releasing an incomplete or faulty product, leading to rework or stakeholder dissatisfaction. Ignoring the request is not an option as stakeholder concerns need to be addressed. Updating acceptance criteria at this late stage is inappropriate and could compromise quality.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed