A project engineer in country A complains a sample from a supplier in country B is the wrong length. During a call, the supplier checked the drawings and insists the measurement is correct. What should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Evaluate the procurement contract to confirm the agreed-upon specifications.
Why this is the answer
The project manager should first evaluate the procurement contract to confirm the agreed-upon specifications. This is a foundational step in conflict resolution and quality management. Discrepancies often arise from differing interpretations of requirements or standards. The contract is the authoritative source for what was agreed upon. Hiring a pre-shipment quality check company is premature; the core issue of differing specifications needs to be resolved first. Escalating to the purchasing department is also premature without first understanding the contractual basis of the dispute. Adding a task to modify the part assumes the supplier is wrong and incurs additional cost and time without confirming the root cause.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed