A project finished ahead of schedule, under budget, and delivered expected benefits. The sponsor distributed recognition certificates but accidentally omitted a key team member. How should the project manager handle the missed team member to avoid disappointment and demotivation?
Choose an answer
Tap an option to check your answer.
Correct answer: Explain the situation to the team member and follow up with a reward and recognition for them..
Why this is the answer
The most effective approach is to directly address the oversight with the team member, acknowledge their contribution, and then provide a tangible reward and recognition. This demonstrates empathy and ensures the team member feels valued despite the initial mistake. Simply inviting them to lunch with leaders might feel like a superficial gesture without addressing the core issue of being overlooked. Thanking them in a public meeting is good, but a personal explanation and a specific reward are more impactful for an individual who was missed. Asking for an additional certificate is a good step, but it doesn't fully rectify the personal slight or provide the immediate, direct acknowledgment needed.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed