A project in execution reports to a program manager and the project manager chairs its steering committee. A steering meeting in two weeks will present how schedule performance to date will be measured. What should the project manager prepare?
Choose an answer
Tap an option to check your answer.
Correct answer: Prepare to explain that the schedule performance index (SPI), schedule variance (SV), and other performance metrics are being used..
Why this is the answer
The project manager should prepare to explain the use of schedule performance metrics like the Schedule Performance Index (SPI) and Schedule Variance (SV). These are standard Earned Value Management (EVM) metrics used to assess schedule efficiency and deviation from the baseline. The steering committee, which the project manager chairs, will want to understand how schedule performance is being measured. Demonstrating cost-benefit ratio, business value, and ROI are important for project justification and overall financial health but are not direct schedule performance metrics. Updating CPI and SPI is part of the work, but the question asks what the project manager should prepare to present regarding how schedule performance will be measured, implying an explanation of the metrics themselves. Claiming schedule performance metrics are not applicable in an agile approach is incorrect; agile projects still track progress and delivery against iterations or releases, often using metrics like velocity or burn-down/burn-up charts, which serve a similar purpose to traditional schedule metrics.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed