A project is delayed because significant rework from a quality problem is affecting the critical path. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Report the delay with rectifying actions to the change control board (CCB) for review..
Why this is the answer
The correct answer is to report the delay with rectifying actions to the change control board (CCB) for review. A significant delay affecting the critical path due to rework from a quality problem constitutes a change to the project's baselines (scope, schedule, and/or cost). Any changes to baselines require formal review and approval by the CCB. The project manager must present the problem, its impact, and proposed rectifying actions to the CCB for their decision. Reporting the delay to the PMO is a good practice but doesn't address the formal change control process required for baseline deviations. Rebaselining the project schedule unilaterally is incorrect; rebaselining requires CCB approval. Informing the project steering committee is also good communication, but it bypasses the formal change control mechanism.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed