A project is in its later stages and all high-level risks from the risk management plan have been resolved or are no longer applicable; only low-level risks remain. What should the project manager do now?
Choose an answer
Tap an option to check your answer.
Correct answer: Reevaluate identified risks and update the risk register..
Why this is the answer
Even in later project stages, continuous risk management is crucial. The project manager should reevaluate identified risks and update the risk register to reflect the current risk landscape. This ensures that remaining low-level risks are still monitored and managed appropriately, as their impact or probability could change. Reclassifying low-level risks as high-level without a change in their characteristics is an arbitrary action that doesn't reflect reality. Notifying stakeholders is a good practice, but it's a communication step that follows the reevaluation, not a substitute for it. Reducing the priority of all remaining risks could lead to complacency and missed opportunities to manage potential issues effectively.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed