A project manager begins receiving emails from various stakeholders asking for project status. What should the project manager do to prevent this in the future?
Choose an answer
Tap an option to check your answer.
Correct answer: Include stakeholders' information needs when planning the project's communications strategy..
Why this is the answer
The correct answer is to include stakeholders' information needs when planning the project's communications strategy. This proactive approach, aligned with Project Communications Management, ensures that stakeholders receive the right information, in the right format, at the right time, thereby preventing ad-hoc requests. Weekly status meetings might be part of a communication strategy but don't address the underlying issue of unmet information needs. Designating a team member to respond is reactive and doesn't solve the root cause. Including stakeholders' emails on all communications could lead to information overload and is not a tailored solution.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed