A project manager consolidates metrics in an agile project and finds team productivity has declined: items sent to development per person dropped 10%. RCA shows a knowledge gap in a modeling framework. What should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Foster knowledge sharing and coaching among team members.
Why this is the answer
Fostering knowledge sharing and coaching among team members is the most effective and agile solution. This approach leverages existing team expertise, promotes internal growth, and addresses the knowledge gap directly within the team's context. It's also cost-effective and builds team resilience. Adding new members might temporarily increase output but doesn't solve the underlying knowledge gap and can disrupt team dynamics. Hiring an external expert is costly and doesn't build internal capability. Arranging external training, while potentially helpful, is a slower, more expensive option that might not be immediately available and could further strain tight schedules.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed