A project manager has run an agile project for six months; over the last two iterations velocity has dropped due to a new technology needed for the product. What should the project manager do to continue delivery and return to expected velocity?
Choose an answer
Tap an option to check your answer.
Correct answer: Use retrospectives to understand how the new technology affects the schedule, identify skill gaps, and adjust the team accordingly..
Why this is the answer
The correct answer is to use retrospectives. Retrospectives are a core agile practice designed for continuous improvement. They provide a structured opportunity for the team to discuss what went well, what didn't, and what can be improved. In this scenario, the retrospective would be the ideal forum to analyze the impact of the new technology, identify skill gaps that are contributing to the velocity drop, and collaboratively decide on adjustments to the team's approach or composition. Requesting additional funding or replacing team members are reactive measures that don't address the root cause or leverage the team's problem-solving capabilities. Reprioritizing the backlog might offer a temporary fix but doesn't resolve the underlying issue of the new technology's impact on velocity.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed