A project manager is assigned to a major construction project important to the city and tied to a local official's election promise. A new sponsor now wants to add aspects the previous sponsor did not support. What should the project manager do next?
Choose an answer
Tap an option to check your answer.
Correct answer: Meet with the new project sponsor to review the current project scope and the requested changes..
Why this is the answer
The project manager should first meet with the new sponsor to understand their perspective and the rationale behind the requested changes. This allows for a comprehensive review of the current scope in light of the new sponsor's vision. Rebaselining the project prematurely is not advisable without understanding the full impact of the changes. Briefing the team without first understanding the sponsor's priorities could lead to miscommunication or wasted effort. Informing the sponsor that changes will not be included is confrontational and dismissive, potentially damaging the relationship and the project's success. Open communication and understanding are crucial at this stage.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed