A project manager is assigned to a project with a long timeline and a complex scope. The client wants both a high-level, long-term plan and something that works immediately, with features added as the project progresses. How should the project manager plan and deliver this project?
Choose an answer
Tap an option to check your answer.
Correct answer: Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver value incrementally..
Why this is the answer
The project requires both a long-term plan and immediate value delivery, indicating a hybrid approach. A predictive approach with a WBS provides the necessary high-level, long-term planning for the complex scope. Subsequently, executing with an agile approach allows for incremental delivery of features, meeting the client's need for immediate functionality and continuous value as the project progresses. A purely predictive approach (second option) would delay value delivery until project completion, not meeting the client's immediate needs. Agreeing on an MVP (third option) is part of an agile strategy but doesn't address the initial need for a comprehensive long-term plan for the complex scope. A purely agile approach (fourth option) might lack the initial long-term planning structure required for a project with a "long timeline and complex scope.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed