A project manager is assigned to lead an infrastructure project spanning several countries and multiple time zones within a subregion. Most team members will likely never meet in person but must collaborate to deliver the project. What should the project manager do to ensure effective collaboration among remote team members?
Choose an answer
Tap an option to check your answer.
Correct answer: Plan a communication method and allow the project team members to virtually interact..
Why this is the answer
The most effective action is to plan a communication method and allow virtual interaction. This directly addresses the challenge of remote teams across time zones by establishing clear channels and opportunities for collaboration. Without a structured communication plan, team members will struggle to coordinate efforts, share information, and resolve issues. Discussing concerns with the sponsor and amending the charter for more budget for interactions is less direct; while budget can help, it doesn't solve the immediate communication challenge. Creating a social media group might foster team spirit but isn't a formal communication plan for project work. Setting ground rules is good, but recording a contingency plan in the risk register is reactive and doesn't proactively establish communication for collaboration.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed