A project manager is leading a hybrid project where the only resources experienced in agile are not at the project manager's location. With a strict schedule and budget, the project manager is concerned about delivery. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Engage the agile resources daily via video conference.
Why this is the answer
Engaging the agile resources daily via video conference is the most practical and efficient solution. This allows for real-time collaboration, addresses the challenge of geographical distance, and leverages the existing expertise without incurring significant additional costs or delays. Informing the sponsor of delays due to training is premature and avoids utilizing available resources. Requesting additional budget for new hires introduces delays and increased costs. Relocating resources is often expensive, time-consuming, and may not be feasible within a strict schedule and budget.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed