A project manager is leading an agile project in an organization with no prior agile projects. To ensure the project meets compliance requirements, what should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Meet with the project management office (PMO)/compliance entity to work on process tailoring to ensure that the agile deliverables support the compliance requirements of the organization..
Why this is the answer
The correct answer is to meet with the PMO/compliance entity to tailor processes. This is the most effective approach because it proactively addresses compliance by integrating agile practices with organizational requirements. Tailoring ensures that the agile project can deliver value while still adhering to necessary regulations and standards, fostering collaboration and understanding between the project team and compliance stakeholders. Using the risk register to document vulnerabilities is a good practice but doesn't proactively resolve the underlying process conflict. Following predictive processes would negate the benefits of agile and is not a suitable solution for an agile project. Coaching senior management and negotiating relief from compliance is unrealistic and irresponsible, as compliance requirements are often non-negotiable legal or regulatory mandates.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed