A project manager is the servant leader for an ongoing project that has historically had unexpected problems. The main stakeholder is hesitant to proceed with remaining sprints even though there are no open issues or risk indicators. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Implement short cycles for inspection and provide feedback.
Why this is the answer
The correct answer is to implement short cycles for inspection and provide feedback. This agile approach, common in servant leadership, directly addresses stakeholder hesitancy by providing frequent opportunities to review progress, demonstrate value, and build confidence. Short cycles (e.g., sprints) allow for early detection of issues, quick adjustments, and continuous validation, which can alleviate concerns about unexpected problems. Logging a new risk naming the stakeholder as a detractor is confrontational and unhelpful; the stakeholder is expressing a valid concern, not acting as a detractor. Increasing management reserves covers known-unknowns and is a financial control, not a solution for stakeholder hesitancy. Increasing contingency reserves covers unknown-unknowns and is also a financial control, not a direct way to build stakeholder confidence or address their concerns about proceeding.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed