A project manager joins a company transitioning to agile. Some stakeholders want the entire project defined and planned upfront, while the sponsor needs a quick win to secure continuation. Which approach should the project manager use?
Choose an answer
Tap an option to check your answer.
Correct answer: Use a hybrid approach to address stakeholders' concerns.
Why this is the answer
The project manager should use a hybrid approach. A hybrid approach combines elements of both predictive (waterfall) and agile methodologies. This allows the project manager to satisfy the sponsor's need for a quick win by delivering early value (agile) while also providing some upfront planning and definition for stakeholders who prefer a more traditional approach (predictive). This balances the conflicting stakeholder expectations and helps manage the transition to agile. An agile approach alone might not satisfy stakeholders who want upfront definition. A purely predictive approach would delay the "quick win" the sponsor needs, potentially jeopardizing project continuation. While a predictive approach demonstrates benefits, it does so later in the project lifecycle, which contradicts the sponsor's immediate need.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed