A project manager joins an agile project with an aggressive timeline and a fixed budget. Most items remain in the backlog and only a few are in progress or complete. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Prioritize which backlog activities should be kept..
Why this is the answer
In an agile project with an aggressive timeline and fixed budget, the project manager's primary focus should be on delivering the most value within those constraints. Prioritizing backlog activities ensures that the team works on the highest-value items first, aligning with the project's goals and stakeholder expectations. Working on backlog activities with fewer story points might seem efficient but doesn't guarantee the highest value delivery. Some high-value items might have more story points. Asking for more resources is often not feasible with a fixed budget and doesn't address the core issue of an unmanaged backlog. Assigning owners and tracking progress is a good practice but comes after prioritization; without clear priorities, the team might still be working on less critical items.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed