A project manager obtained market information indicating the ongoing project's business value will be reduced. The project manager believes the project should be stopped. How should they handle the situation?
Choose an answer
Tap an option to check your answer.
Correct answer: Have a discussion with the sponsor and recommend the project business value be reassessed..
Why this is the answer
The correct approach is to discuss the market information with the sponsor and recommend a reassessment of the project's business value. As the project manager, you have a responsibility to inform stakeholders of significant changes that impact project viability. The sponsor is ultimately accountable for the project's business case and strategic alignment. Reassessing the business value allows for an informed decision on whether to continue, modify, or terminate the project based on current market realities. Discussing with the sponsor and immediately canceling the project is premature; the sponsor needs to be involved in the decision-making process. Removing items from the backlog is an operational task that doesn't address the fundamental issue of reduced business value. Proceeding with the current scope and only reviewing the risk matrix ignores the core problem of the project's strategic justification.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed