A project manager takes over a project mid-execution. The sponsor asks to ensure the work and product remain aligned with the intended business value. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Review the benefits realization plan..
Why this is the answer
The correct answer is to review the benefits realization plan. This plan outlines how and when the project's intended benefits, which directly link to business value, will be achieved and measured. By reviewing it, the project manager can understand the project's strategic objectives and ensure ongoing work aligns with delivering those benefits. Reviewing the requirements management plan is important for managing requirements, but it doesn't directly address the business value of those requirements. Monitoring the WBS ensures the scope is managed, but not necessarily its alignment with business value. Conducting quality audits and failure analyses focuses on product quality and defect prevention, which supports value but isn't the primary document for understanding and ensuring business value alignment.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed