A project manager was transferred to another country, completed planning, and began execution with good progress. At a sponsor meeting, stakeholders complained the manager's emails are very harsh. What should the project manager do to resolve this?
Choose an answer
Tap an option to check your answer.
Correct answer: Modify the communications management plan to rebuild stakeholder trust..
Why this is the answer
The correct answer is to modify the communications management plan because communication is a critical component of stakeholder engagement and trust. The project manager's current communication style is causing issues, indicating a need to adjust the approach to align with local cultural norms and stakeholder expectations. Updating the plan ensures a structured and agreed-upon strategy for future communications, helping to rebuild trust and improve project success. Assessing stakeholder influence is a continuous process but doesn't resolve the immediate communication problem. Switching to meetings might reduce email complaints but doesn't address the underlying issue of communication style and could be inefficient. Explaining that the style is dictated by headquarters is defensive and doesn't solve the problem; effective project managers adapt to their environment.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed