A project manager working on a critical path activity identifies a delay in product delivery due to a foreseen event. What should the project manager do first?
Choose an answer
Tap an option to check your answer.
Correct answer: Follow the risk response plan..
Why this is the answer
The correct answer is "Follow the risk response plan." Since the delay was due to a foreseen event, it indicates a known risk that should have a pre-defined risk response plan. The project manager's first action should be to execute this plan to mitigate the impact of the risk. "Use the contingency fund" might be part of the risk response plan, but it's not the first action; the plan itself dictates when and how funds are used. "Update the risk register" is important, but it comes after initiating the response to the immediate risk. "Prepare a change request" might be necessary if the risk response plan proves insufficient or if the project baseline needs adjustment, but the initial step is to implement the existing plan.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed