A project's scope is to replace street signs within a 10-km radius. The client refuses to sign the project closure report unless the radius is extended by 1 km to align with the council's development plan. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Obtain formal acceptance for the completed work and submit a change request..
Why this is the answer
The correct approach is to obtain formal acceptance for the completed work and submit a change request. The project has delivered its defined scope (10-km radius), and the client's refusal to sign off is based on a new requirement. The project manager must secure formal acceptance for the work already completed to close the current project phase or the project itself. The request for an additional 1 km is a scope change that needs to go through the formal change control process. Delaying closure and asking for additional funding is premature without a formal change request. Contacting the council to extend the scope bypasses the necessary internal project change control. Initiating a new project is an option for significant, separate work, but a change request is appropriate for an extension of the current project's scope.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed