A project scope statement was approved and the core team assigned. The project manager took a temporary medical leave while the team developed a detailed schedule, which is nearly complete on the manager's return. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Ensure the schedule aligns with the project's vision and objectives..
Why this is the answer
The project manager's primary responsibility upon returning is to ensure the developed schedule accurately reflects the approved scope and project objectives. This involves validating that the detailed tasks, durations, and dependencies support the project's vision and will deliver the intended outcomes. Without this alignment, the project risks delivering the wrong product or failing to meet stakeholder expectations. Escalating a compliance concern is premature as no non-compliance has been identified. Congratulating the team and proceeding directly to execution skips a critical validation step, potentially leading to rework later. Creating a new schedule from scratch would be inefficient and disregard the team's completed work, wasting valuable time and resources.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed