A project sponsor insists the project scope include two geographic locations, but the approved project charter includes only one. What should the project manager do?
Choose an answer
Tap an option to check your answer.
Correct answer: Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project..
Why this is the answer
The project charter formally authorizes the project and defines its high-level scope. Any changes to the approved charter, including scope modifications, must go through the formal change control process. The project manager should first assess the impact of adding a second location on all project constraints (scope, schedule, cost, quality, resources, risks) and then submit a change request. This ensures the change is properly evaluated and approved before implementation, maintaining project control. Simply asking for more budget/schedule is premature without a full impact assessment. Telling the sponsor it's not possible without following due process is incorrect. Suggesting a separate project bypasses the current project's governance and the sponsor's immediate request.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed