A project team is delayed on a task that proved more complex than estimated. This critical task could affect the current iteration goals. Which two initial actions will help the team address this obstacle? (Choose two.)
Choose an answer
Tap an option to check your answer.
Correct answer: Review and update dependencies, Conduct a root cause analysis.
Why this is the answer
When a critical task is delayed due to unexpected complexity, the team needs to understand why and assess the impact. Conducting a root cause analysis helps identify the underlying reasons for the complexity and delay, preventing recurrence and informing potential solutions. Reviewing and updating dependencies is crucial because a delay in a critical task will likely affect subsequent tasks. Understanding these updated dependencies allows the team to re-plan and mitigate further schedule impacts. Escalating to the project sponsor is premature; the team should first attempt to resolve the issue internally. Scheduling a retrospective is typically done at the end of an iteration or project, not as an immediate action for a current obstacle. Creating a risk management plan is a proactive activity performed earlier in the project lifecycle, not a reactive step for an immediate problem.
Pass your exam — without the endless answer hunt
Get every verified question and explanation for this exam in one place, and save hours of prep. 1,000+ certifications · 20+ languages · free to start.
Pass your exam faster → No card needed